Tap and Drain Services

Controlled tap and drain of glass furnaces with or without water recycling-system

alt

>> Step 1

Furnace Drilling with a diameter of 80 – 100 mm

alt

>> Step 2

Installation of safety- and regulating device
alt

>> Step 3
Installation of a drain channel up to 60 metres length

alt

>> Step 4
Furnace Drain with 10 – 25 tons per hour.

alt

>> Step 5
Cooling unit - to be used on recycling drains for cooling of the water from appr 90°C down to 40 - 50°C

alt

>> Step 6
Furnace drain with water recycling system. This system filters the main water quantity and refeeds it to the draining procedure. Only lost water (by vaporation) has to be refilled, appr. 15 – 20 %. By the use of the recycling system, draining quantity amounts to 10 – 15 tons per hour.

alt

>> Step 7

In order to be able to drain bigger quantities, 2 recycling systems can be installed in paralell.